KazMunayGas (KMG) and Italy's Eni have inaugurated a 120 MW gas-fired power plant in Zhanaozen, in Kazakhstan's Mangystau region. According to Trend, the inauguration took place on 24 November 2026, two days before it was reported.
The plant is the second piece of a 247 MW hybrid complex that will combine gas, solar and wind power. Its main job is practical: to give KMG's oil and gas facilities in Mangystau a steadier supply of electricity.
The complex has three parts. A 50 MW solar plant was commissioned in September 2025. The 120 MW gas plant is now in service. A 77 MW wind farm is planned to start work in 2027, according to Eni's press release of 22 July 2026. Trend says the project also includes a substation and a 110 kV transmission line.
The gas plant first produced "first industrial electricity" in July. KMG's own press release from that month says the plant uses six Wärtsilä gas piston units and a 110 kV substation. It said more than 1,000 people were working on the site. Trend now reports that commercial generation began in July and that the gas plant has produced more than 26 million kWh since then. The solar plant has produced about 93 million kWh, Trend says. In July, KMG put solar output at about 62 million kWh, so the figure has grown since.
The electricity goes to KMG subsidiaries. Trend names OzenMunayGas and KazGPP as facilities the complex is designed to supply. Eni says its subsidiary Plenitude developed the project with KMG. Eni also holds stakes in Karachaganak, the North Caspian project, CPC and BTC in Kazakhstan.
KMG and Eni signed an agreement on joint project principles in Astana in June 2023, according to Trend. Construction in Zhanaozen began in 2024. The project falls under KMG's low-carbon development programme, KMG says. Trend adds that, once the wind farm is running, renewables should supply about 35% of the complex's generation.
This is not a pure clean-energy project, and it should not be read as one. Gas provides most of the capacity: 120 MW of 247 MW, or about 49%. The reason is reliability. Solar and wind output changes through the day and the season. Oil fields and gas processing plants need power all the time. A gas plant fills the gaps and lets the operator accept the variable renewables.
For KMG, the benefit is a local source of electricity for its regional subsidiaries, as Eni and KMG describe it. For Eni, the project sits alongside its upstream stakes and the Plenitude wind and solar plants it already has in Kazakhstan.
There are open questions. Neither company has published the cost of the complex in the material we reviewed. The 247 MW figure comes from Eni, KMG and Trend. The 35% renewable share depends on the wind farm, which has not yet been built.
The first test is the 77 MW wind farm, due in 2027. Any delay would leave the complex more dependent on gas than planned. Watch also whether KMG and Eni announce similar hybrid plants for other fields, and whether the Mangystau plant's output figures are published in a regular report.
Sources: Trend, 26 November 2026; Eni press release, 22 July 2026; KazMunayGas press release, July 2026.
Image: Caucasus Business Journal archive graphic, via caucasusbusinessjournal.com