bp has said it expects to take a final investment decision (FID) on the Karabakh oil field in the Azerbaijani sector of the Caspian Sea in 2027, according to APA on 19 November 2026. Bakhtiyar Aslanbayli, bp's Vice President for the Caspian, Central Asia and Türkiye region, said the decision is expected to be made next year, and that it is difficult to say exactly when construction could begin.
The statement matters because Karabakh would be a rare new-field development in a basin dominated by ageing giants. It comes as operators in Azerbaijan look for ways to extend oil output beyond the mature Azeri-Chirag-Gunashli (ACG) complex.
The field is held under a Risk Services Agreement signed in 2018, according to APA. In June 2025 bp completed the acquisition of a 35 per cent stake, with SOCAR keeping 65 per cent, and bp became operator, according to bp's own press release of 3 June 2025. The release gives no reserve or production figures. Equinor is not part of the venture: S&P Global reported in June 2025 that Equinor left its Azeri assets in 2024.
No official reserve number has been published. Aslanbayli has said the field's reserves are significantly smaller than ACG's, as APA reported on 8 October 2025, and that this makes cost control central to the project's commercial case. S&P Global noted that SOCAR has cited several hundred million barrels, while bp has not confirmed expected volumes. Treat that as a loose indication rather than a certified estimate.
The same October 2025 report places Karabakh about 120 kilometres east of Baku and 20 to 25 kilometres from the Gunashli field, in water 150 to 200 metres deep. On the cost approach, bp says that rather than laying pipelines piece by piece offshore, it is studying a "bundle" method: 7 kilometre sections of oil and gas pipelines and electrical cables assembled onshore, towed out and installed, with further sections added in sequence. The company says this is cheaper. Whether a platform will be built at all is still under study.
The schedule has moved in the right direction but slowly. In October 2025 the project was at the concept development stage. In June 2026 Giovanni Cristofoli, bp's regional president for Azerbaijan, Georgia and Türkiye, said bp aimed for FID around the middle of 2027, per APA on 2 June 2026. The latest wording, simply "next year", is less specific than the June 2026 timing. Preparatory work is under way at Bandovan, covering permits, land allocation and access roads for a construction site.
S&P Global reported in June 2025 that bp was aiming for first production in 2029. That ambition now looks tight if FID slips through 2027 and construction follows.
Three things will decide the outcome: the concept selection, in particular platform versus tie-back to existing infrastructure; a published cost and reserve basis; and any SOCAR statement on its 65 per cent share of the financing. Karabakh also sits alongside bp's wider push to extract more from ACG, which we covered in SOCAR and bp See ACG Oil Recovery Above 40%. If the bundle concept proves out, it could set a template for other small Caspian discoveries.
Sources: APA, 19 November 2026; APA, 2 June 2026; APA, 8 October 2025; bp, 3 June 2025; S&P Global, 3 June 2025.