Six weeks after the presidents of Azerbaijan and Kazakhstan switched it on, the first fibre-optic cable laid across the Caspian seabed gives Central Asia a direct westbound data route that bypasses Russian networks. The cable is late, costs less than it sounds, and it is only the first link in a longer chain.

On 15 October 2026, President Ilham Aliyev and President Kassym-Jomart Tokayev jointly inaugurated, in an online ceremony, the Trans-Caspian Fiber-Optic Cable between Sumgayit in Azerbaijan and Aktau in Kazakhstan (The Astana Times; President of Azerbaijan). "This is a new type of corridor. It is not a transport corridor, but something new that fits into the modern era, the era of digitalization," Tokayev said at the launch.

The cable in numbers

  • Route: Sumgayit (Azerbaijan) to Aktau (Kazakhstan), along the seabed of the Caspian Sea.
  • Length: about 380 km of armoured submarine cable. Kazakhstan's digital development minister Zhaslan Madiyev put the laid length at "some 390 kilometers" (Interfax, 6 Oct 2026).
  • Design capacity: more than 400 terabits per second (Caspian News, 21 Oct 2026).
  • Owners: a joint venture of AzerTelecom, part of Azerconnect Group within NEQSOL Holding, and Kazakhtelecom, Kazakhstan's national operator. The venture builds and operates the line; it is named CaspiLink B.V. in 2026 reports and was reported as Caspinet B.V. when it was registered in August 2023 (Interfax; The Astana Times, Aug 2023).
  • Funding: the operators' own funds, without state budget money, according to Interfax. Madiyev said in June 2024 that the project would cost more than 23 billion tenge, about $50 million (Interfax, 18 Jun 2024).

Why a 380 km cable matters

The case for the cable is not speed alone. Approximately 95 percent of Kazakhstan's web traffic has transited Russian networks, and Kazakh internet providers source roughly 80 percent of their international bandwidth from Russian operators, according to figures compiled by the Jamestown Foundation's Eurasia Daily Monitor from 2022 data. Uzbekistan's external links run through Kazakhstan and then Russia.

Routed west through Azerbaijan, Georgia and the Black Sea, the Caspian link creates what the same analysis calls "the first sovereign east–west digital pathway out of Central Asia". The Astana Times reported that the line could also connect with submarine systems in the Mediterranean and Black seas.

The Kazakh side frames it as an investment magnet: the cable is expected to help attract global technology companies, cloud services and AI infrastructure to Kazakhstan. That ambition meets a hard ceiling. Kazakhstan, Uzbekistan and Kyrgyzstan together host just over 4,700 data-centre racks, and only 15 facilities are certified Tier III by the Uptime Institute (Carnegie Politika, Apr 2026). The cable does not fix that gap, but without an independent route out, new data-centre capacity would still depend on Russian transit.

Seven years from groundbreaking to service

The project is part of the Digital Silk Way, a programme NEQSOL Holding launched in 2018 to build a terrestrial and subsea fibre corridor through Azerbaijan, Georgia, Türkiye, Kazakhstan and Turkmenistan (Digital Silk Way). The holding has valued the wider programme at more than $250 million (Business Wire, Mar 2025).

  • November 2019: groundbreaking in Aktau with earlier Kazakh partners, with completion then targeted for the end of 2021.
  • September 2022: AzerTelecom and Kazakhtelecom sign a strategic partnership memorandum in Astana (Digital Silk Way).
  • August 2023: the two operators agree to register the joint venture.
  • March 2025: construction agreement signed and first construction phase launched.
  • July 2026: cable laying on the seabed begins (Interfax).
  • August 2026: installation of the 380 km cable from Sumgayit to Aktau completed (Submarine Networks, 9 Aug 2026).
  • 15 October 2026: official launch by the two presidents.

The five-year slip against the 2019 target was attributed to partner changes, joint-venture restructuring, the pandemic and the 2020 oil price collapse, according to Eurasia Daily Monitor.

When construction began in March 2025, Yusif Jabbarov, then chief executive of NEQSOL Holding, described the line as the "most optimal and shortest route between Europe and Asia" (NEQSOL Holding). At the launch, Jabbarov, now chairman of the board, called it "a strategic investment in Eurasia's digital infrastructure" (Caspian News).

What comes next

The Azerbaijan–Kazakhstan line is phase one. A second phase foresees a similar seabed cable on an Azerbaijan–Turkmenistan route, which would add a second east–west path and redundancy for the first (Submarine Networks). Turkmenistan has long preferred bilateral frameworks, and that segment is handled through the Azerbaijan–Turkmenistan intergovernmental commission rather than regional summit declarations.

On the western end, NEQSOL, through Vodafone Ukraine, works with Vodafone Group on the Kardesa submarine system linking Bulgaria, Georgia, Türkiye and Ukraine across the Black Sea. Together with the Caspian cable, it is designed to give the corridor an onward path to European networks.

The test from here is commercial rather than ceremonial: how much of Central Asia's international traffic the operators actually move onto the new route, and at what price compared with the established northern links. Neither operator has published traffic or pricing figures since the launch.

Further Reading

Image: Caucasus Business Journal

Disclosure: the publisher has a commercial relationship with an organisation mentioned in this article.

Featured Offer
Unlimited Digital Access
Subscribe
Unlimited Digital Access
Subscribe
Close Icon
Webflow Icon