Azerbaijan Railways (ADY) has opened an international tender for a new SAP S/4HANA enterprise resource planning system, the core of a digital overhaul financed by the Asian Development Bank. The invitation for bids was posted on 20 November 2026 on the ADB project page, which sets the closing date at 6 January 2027.
The tender matters because it moves the state railway's digital programme from preparation into its largest single piece of software. ADY is carrying sharply higher transit and container volumes, and the company's planning, asset and customer systems will need to keep pace with that traffic.
According to the tender terms reported by Trend, the winning supplier will design and run the full implementation: solution architecture, configuration, integration, data migration, testing, staff training and post-launch support, plus all SAP licences and subscriptions. Implementation is set at 18 months, with go-live no later than the end of month 15 and stabilisation support in months 16 to 18. A 12-month warranty follows, giving a total contract period of 30 months.
The bar for bidders is set high. Technical quality carries 80% of the evaluation weight and price 20%. Lead suppliers need an average annual turnover of at least $4m over three years, at least $500,000 in liquid assets or credit, and either one completed contract worth $10m or two worth $5m each in the past five years. There is no preference for domestic bidders. Bids are due at 3pm Baku time on 6 January at ADY's head office.
The work is funded under ADB Loan 4497-AZE, a $47m loan from ordinary capital resources approved on 30 September 2024 and effective since 10 March 2025. The project aims to bring ADY's main business processes, from transport management and asset management to investment planning, freight customer handling and corporate functions, into one integrated management data system.
Progress so far has been gradual. As of 6 August 2026, contract awards stood at $16.07m, or 34% of the loan, and disbursements at $12.69m, or 27%, the ADB page shows. Earlier contracts covered a freight and commercial operations system, signed with Eurodesign CJSC in July 2025, and an IT equipment contract with Caspel LLC in March 2025, while a separate tender for an SAP SuccessFactors human resources system closed in October 2026. ADB data cited by Report put total spending at $6.163m by the end of 2025.
The ERP contract is the backbone of the programme, and its timetable leaves little slack. The ADB page lists the loan's closing date as 31 December 2028. If a contract is signed in the first quarter of 2027, a go-live at the end of month 15 would fall in mid-2028, so any delay in evaluation or data migration would press against the loan's end date.
Demand is not the problem. ADY carried 15.691m tonnes of freight in January to October 2026, up 13% on a year earlier, with transit cargo up 20% to 6.582m tonnes, the company told APA. Container traffic rose 18% to 132,500 TEU, and the railway received 472 block trains from China, up 49%. Volumes of that kind raise the cost of running freight operations on fragmented systems.
The key dates are the 6 January bid opening and the contract award that follows. Watch also for any extension of the loan's closing date, the go-live of the HR and freight modules already procured, and whether ADY publishes data showing faster wagon turnaround or border handling once the new systems are running.
Sources: Asian Development Bank, 58049-001: Azerbaijan Railways Digital Transformation Project; Trend, Azerbaijan Railways announces ADB-backed tender for digital ERP system; APA, Azerbaijan records sharp increase in freight trains received from China; Report, Azerbaijan Railways' digital modernization spending tops $6M by late 2025