Azerbaijan has started building a 235 km, 500 kV power line between Mingachevir and the Navahi substation, APA reported on 23 November 2026. The line is part of the second phase of the World Bank-backed Azerbaijan Scaling-Up Renewable Energy Project, known as AZURE. APA says it will help integrate new renewable plants into the national grid and form a 500 kV ring across the west, centre and east of the country.
APA gave no cost, capacity or completion date for the line.
Azerenerji's non-technical summary of AZURE describes a 235 km single-circuit 500 kV overhead line from the Azerbaijan thermal power plant substation to Navahi. It also covers 500 kV equipment at Navahi (2 x 500 MVA) and extra 500 kV bays at Absheron and at the thermal plant. This 500 kV strengthening is budgeted at US$134.6 million, and a May 2026 Power Line report cited the same figure.
Power Line puts the World Bank loan for AZURE at US$173.5 million. The summary lists US$168.4 million for grid works and US$5.1 million for implementation support. According to APA, second-phase work also includes three 330 kV lines toward Alat, Absheron and Gobu, with construction due to begin in the near future. The summary lists them at 22 km, 65 km and 19 km.
The summary says the works are designed to evacuate 1 GW of variable renewable power connected at Navahi, even if one element fails, and to help manage fluctuations from 1.8 GW of such capacity in the system. Named projects include 315 MW of solar at Banka and 445 MW at Bilasuvar, both planned for 2026 and 2027, and a 240 MW Absheron wind plant due by 2028. The first phase has already delivered the Navahi Green Energy Hub substation and 330 kV connections to the Bilasuvar and Banka solar plants, according to APA.
On 22 October Trend reported that Energy Minister Parviz Shahbazov discussed AZURE with the World Bank. It described the aim as connecting 2 GW of renewable capacity under construction to the grid, and said the second phase is expected to take three years. The sides also discussed cooperation on the Caspian-Black Sea-Europe Green Energy Corridor.
Sources: APA, Azerbaijan develops new 500 kV high-voltage energy corridor; Azerenerji, AZURE Project Non-Technical Summary; Trend, Azerbaijan, World Bank discuss AZURE project and Green Energy Corridor; Power Line, Azerbaijan's Azerenerji to develop 500 kV line under AZURE project